Seawall Repair Update – 1/6/25

The beach renourishment contractor, SJ Hamill, continues the seawall repair work in the area of Beach Club Villas and Dolphin Point. They are currently averaging 200 tons of armor stone delivery per day from the quarry. This section of the seawall requires around 6,000 tons of stone repair. The contractor is approximately 50% complete and they should be done with this section of seawall by the end of February.

They will begin setting up the staging area for the final section between Boardwalk 8 and the Beach Club in mid-January. Seawall repairs in this section will begin after Beach Club Villas and Dolphin Point are complete and continue into April.